The Story of the Barn Conversion
January 2019
We started on site on the 9th January, with Andy and two of the team from Carrock Design, Dan and John
The initial work was to get the site prepared
Carrock Design Build
The builders arrive (Wednesday 9 Jan). The first thing they do is put up their cabin. Heath and Safety requirement; they need to stay warm and dry (a challenge in the Cumbrian winter).
Boulders
Just below the surface we find a layer of stones/boulders. In a way, this is a good thing as we need these to build a new dry stone wall (planning requirement). Thank goodness the building supplies delivery driver arrived and moved the biggest obstacle with his hydraulic lift.
The Path
Getting tools and materials to the barn is a challenge - the building is on a steep slope.
In December we spent a week digging out a path from the road, traversing the slope to reach the top part of the barn.
Boys Toys
The builders bring along lots of "boys toys". Andy is particularly impressed with the big yellow motorised wheel barrow.
Oil Tank base
We became aware that the house uses too much electricity (it had electric heating) and there wasn't enough to power the barn. To reduce the house usage, we are putting in oil fired central heating. Andy has dug out and is now filling the based for the oil tank.
Mini digger
The mini digger putting in the trench for the electric supply from the house to barn. Bad news for Andy - you need a digger driver qualification to use it so he has to stick with the a shovel.
Knocking down a wall
Andy and Dan (joiner) taking a break from knocking down the internal wall in the lower half of the barn. almost ready for the mini digger to excavate and start under pinning.
Boiler base
It is Saturday. Andy is digging out the external boiler base and the plumber is here too trying to get all the new radiators in place. The electricians took the electric radiators out on Wednesday.
Digging the drains
The big digger has arrived and is excavating for the drainage and new water supply for the house and barn.
Digging out the barn floor
Digging the ground floor out so that we have enough height to stand up. Not sure yet how far the stone wall goes down and how much underpinning will be required.
Broken drains
Just when it seemed to be going so well... We were checking that the toilets in the house all went into our sewage chamber. Found that one was blocked and the pipe cracked. Poor Andy volunteered to clear it out and take out part of the wall to expose the broken pipe (which runs under the kitchen floor).
Hoping the plumber can fix it.
The wall came tumbling down
Digging a channel under the wall for the rain water drainage and it came tumbling down. Lucky only a spade was buried.
Toasty!
After a weekend in Whipsnade, we arrived back at High Brow to find the new oil fired boiler and central heating was working. Toasty!
Andy just tidying up around the external boiler and oil tank.
Slow week
Not too much progress this week as snow prevented the builders from getting to us.
The weather has given us some fantastic sunrises though.
Repointing inside the barn
Due to the weather, we are doing inside jobs. One of these is to plug the gaps in the internal stone wall of the barn to strengthen it. Hoping this helps the stones stick together and not fall down!
February 2019
Despite some weather challenges we make good progress
March 2019
Snow and then torrential rain hold us up a little, but good progress made
More snow!
It is Friday 1st February and 3 more days lost due to snow.
The scenery is lovely though.
Under-pinning
The 6th Feb and the snow has gone. All action again including the start of the under-pinning.
Propping up the door
When we excavated by the door, we found a piece of rotting wood holding up the wall. Once the foundations set, we can rebuild that part of the wall.
More drainage
The chamber for the surface water drainage is in place. This will help to stop the barn from flooding.
Mini collapse
A small section of the wall collapses during the under-pinning - more rebuilding to do. Andy comments that it is the ONLY section he did not dig out...
Sewage System
The new sewage treatment plant has arrived and ready to install.
Sewage in situ
The sewage tank is in place and being encased in concrete and soil.
Digging the drains in the barn
The drains in the barn are in place for the kitchen sink and bathroom.
Walling
Andy has started to rebuild the dry stone wall that collapsed a few weeks ago. Slow and steady progress, but looking good.
New water supply
The water company have finally connected us directly to the water mains. We had been sharing a single supply with next door so the pressure wasn't great.
March 2019
Good progress made, focussing on the structure of the building
Concrete lorry
The 5th March and the concrete mixer and pump arrived. The pump negates the need to wheel barrow the concrete down the slope a bit at a time. It takes 2 hours but much quicker than the manual option.
Laying the slab
The concrete is "tampered" using a long horizontal metal bar, to make it lovely and smooth.
Scaffold
The scaffold is up ready for the roofers and for us to start the re-pointing.
Starting the windows
Starting to knock through to make the new window openings.
Break Through
The extra window openings in the lounge have been made. Waiting for the windows.
April 2019
Tanking to keep the water out completed, then start the framing out ready for insulation and plasterboard. Building regs for insulation mean that we have to cover up all the internal stone
Wall Battens
First battens in place following completion of the tanking
Tanking
Waterproofing the walls and ground floor - we are assured that the river off the fells that came through the barn in february will now pass round and under !
Roof Insulation
Insulation installed - accurate cutting required or it falls out! (Andy only made that mistake once..)
Roof Lights
The roof lights are in.
The roofers are here and repairing the roof where required.
The plasterers started last week on the tanking.
A flue
The flue for the log burning stove is in place. We are a little way off having the stove fitted though!
May 2019
Progress being made - first fix electrics and plumbing completed, scaffolding down and walls spray foamed for insulation. We finally found our missing roofers, who turned up and did a great job, as illustrated by the front porch below. The underfloor heating pipes are in and first floor screeding completed by Andrew, whilst Jacquie keeps pointing ! Planning issues over the air source heat pump siting have been resolved...after five months! Staircase has arrived, to go in next week and we begin plasterboarding friday.
Spray Foam Insulation done
Now we can be warm...
Scaffolding Down!
Still a building site, but further progress; Jac's pointing is very evident in this photo
Roof
Front porch roof completed and all roof repairs finally done - worth the wait...
Ground Floor Wall Frames
First frames installed for the bathroom
Floor
Floor insulation laid
Pipes
Underfloor heating pipe installed
Screed
Andrew's floor screeding
June 2019
Watertight at last, with doors and windows installed. Andrew and Jacquie have been plasterboarding for weeks.
Front Porch
Doors installed
South Side
New door and window and expert pointing by Jac
West Side
New window
East Side
Door installed, essential pointing done
Stairs Installed
Partial balustrade, spindles to follow
Lounge
Weeks of plasterboarding by Jac and Andrew
Bathroom
Tiling in progress
July 2019
Plastering on and off for several weeks, but hope to complete this week. Bathroom has working facilities and virtually complete. Air Source Heat Pump and Water heating systems commissioned. External steps being built. We even got out walking and running a little this month.
Lounge
Plastering progressing
Bathroom
Tiling nearly complete
Bathroom
Expert tiler!
Steps
Road to nowhere...start of path to main entrance
Air Source Heat Pump
Commissioned
Ecocent
Big tank recirculates warm air to heat water
August 2019
We took some time off, but some further progress made
Tiling the porch
We took a some time out this month but Andy tiled the porch and kitchen area with slate tiles.
September 2019
We spent most of this month waiting for the various trades people to turn up. Andy spent the time building the external steps and I cleaned oak beams and painted the walls.
Top patio
The main patio with slate tiles
External steps and path
Ready to cover in slate
Internal stairs
Painting the internal stairs
October 2019
The Dry Stone Wallers called to say they could start in mid- October.
On our way home at the end of October, the joiner rang to say he could start! Andy managed a weekend at home before going back to the Lakes.
Lower wall
Andy admiring the start of the lower dry stone wall
Completed lower wall
The finished lower wall. The wallers had to go to a dry stone walling emergency. Due back in November
A pile of stones
The next pile of stones for Andy to sort out ready for the upper wall
Bathroom door
We now have doors on the bathroom
Stairs
A few more spindles, this time put in place by Andy (under supervision).
November 2019
We have finally finished the internal work and external building, just an external handrail to go...and hopefully building regs signed off early January. In the spring we will add external shutters to ensure it looks like a traditional Lakeland field barn in it's setting. It's been hard work, but now time to enjoy walking, running and spending time relaxing in our retirement! We have external landscaping to do, but aim to take our time over that in the spring.
Back to Fell Running !
Blencathra from Clough Head - Andy can still get up there, but slowly...
Barn from our field
Finished building externally
Lounge and Beams
Amazing what you can do with Wire Brushes and elbow grease!
Ballustrades
They were fun pulling in!
Kitchen
Same design as house...
Bathroom
Nice big shower!
Hobbit Door for Jac
Eventually Andy will learn to duck!
Expert Step Building by Bob and Andy
Hopefully will meet Building regs...
Andy's Wall
It's still up...
Top Dry Stone Wall
Up in three days, the stone shifter had to work hard...